Background Image
Previous Page  7 / 14 Next Page
Information
Show Menu
Previous Page 7 / 14 Next Page
Page Background

Business View Australia - June 2015 27

CONSTRUCTION

contracts. Even though the works

were in two separate geograph-

ic locations about 40 km apart,

the projects were combined to en-

sure a commonality of equipment

between the two sites. The value

of this project was $77 million.

In the normal course a contrac-

tor who was large enough would

have taken on this project and in

turn, awarded sub-contracts. How-

ever, the Council decided to take

this role upon itself and conse-

quently split the project into “pack-

ages” and awarded the contracts

for similar work at the two sites.

Greg Mashiah describes how the

Council utilized this technique to en-

sure the successful implementation of

the project, “We have been very for-

tunate here that all our projects have

been successful, but we have also tak-

en lessons from each of the projects.

For example, one of the things that

we did on the first project was that we

split it up into five separate contracts.

The value of the project was such

that if we had let the whole augmen-

tation as a single contract it would

have been within the financial capa-

bility of only the largest contractors,

because it was about $77 million in

total. So by splitting it up into sev-

eral contracts, the largest award-

ed was just about $40 million. On

the Iluka project we, as a result of

lessons learnt, reduced that from

four contract packages to three.”

Another technique used by the Coun-

cil was the Early Tendering Involve-

ment which was initially developed

by New South Wales Public Works for

Council’s Shannon Creek Dam proj-

ect in 2005. This technique involves

short-listing potential construction

contractors through an Expression

of Interest process. A meeting is

then held with these potential con-

tractors to reply to any questions

that they may have and describe

the details of the contract to them.

Explaining the benefits of Early Ten-

dering Involvement, Greg Mashiah

says, “Another thing that we have used

quite extensively is that all the tenders

have been awarded using a process

where potential contractors who have

been short-listed at the beginning of a

project are given an initial risk alloca-

tion and each is requested to provide

feedback on both design and risk al-

location to ensure that risk is placed

with the party best able to manage it.

We found the process extreme-

ly successful because we believe it

has mitigated the cost of unknown

risks and risks are placed with the

party best able to manage them.”